WI Point Road to Close
Road Work Prompts Temporary Closing of Wisconsin Point Road
Wisconsin Point Road will be closed Monday, August 24 through Wednesday, August 26th (weather permitting) for Cold In-place recycling (CIR) of asphalt on portions of the road.
According to Todd Janigo, director of Public Works, “The CIR process mills and picks up 3” of existing asphalt/gravel, crushes and screens the material, injects foamed asphalt, places the mixture with a paver and then re-compacts the material.”
This readies the road for City crews to lay a final overlay two weeks later after the material sets.
When City crews arrive in September, they will use a flag person so the road will remain open during the final paving.
If it should rain early in the week of August 24th, the 3-day road closure could be delayed.