Several Hundred People Address Enbridge Pipeline Reroute
MADISON, Wis. (AP) — Many of nearly 300 people who attended a 10-hour-long virtual public hearing spoke against a $450 million plan to reroute an oil and gas pipeline across northern Wisconsin.
The hearing that began Wednesday finally wrapped up early Thursday. Participants addressed a draft environmental review for a 40-mile reroute of Enbridge’s Line 5 in Ashland and Iron counties.
The pipeline carries up to 23 million gallons of oil and natural gas liquids per day and spans 645 miles from Superior to Sarnia, Ontario, Wisconsin Public Radio reported.
Enbridge wants to move the pipeline after the Bad River Band of Lake Superior Chippewa sued the company in 2019 to shut down and remove the pipeline from the tribe’s reservation.
Environmental groups, tribal members, activists, and residents from across the state, Midwest, and beyond argue the DNR’s draft environmental review is insufficient and doesn’t adequately evaluate impacts along the route that include the risk of spills.
“The draft (environmental impact statement) doesn’t properly recognize how harmful Enbridge’s proposal for a new Line 5 segment would be to Wisconsin’s waters, wetlands or climate,” Jennifer Giegerich, director of government affairs for Wisconsin Conservation Voters, said. “Secondly, this draft EIS fails to recognize the authority of the treaty rights of the tribes of Wisconsin.”
Republican lawmakers, labor unions, and the state’s largest business lobby support the project, citing the 700 construction jobs it would generate.
Enbridge needs permits from multiple state and federal agencies to move ahead with the project.